Does a Construction Project Begin at Execution? At Contract Signing? Or Even Before?
هل يبدأ المشروع عند التنفيذ؟ أم عند توقيع العقد؟ ام من قبل ذلك؟

Marketing & Branding

Does a Construction Project Begin at Execution? At Contract Signing? Or Even Before?

Does a Construction Project Begin at Execution? At Contract Signing? Or Even Before?

2026-05-25
0 Comments
هل يبدأ المشروع عند التنفيذ؟ أم عند توقيع العقد؟ ام من قبل ذلك؟

🏗️ From the Reality of Contract Management in Construction Projects

Many of the challenges in construction projects don't begin on site… They begin at the stage of forming the contractual relationship itself.

And to be even more precise — they begin at the Pricing Stage, before the award is made and before the Contractor is accepted.


📕 Under FIDIC Red Book Contracts (Traditional Projects)

In FIDIC Red Book contracts governing traditional construction projects, the project lifecycle passes through several interconnected stages, beginning long before the first shovel breaks ground:


1️⃣ Tender Stage

📋 Defining the foundation of the entire contractual relationship

This stage involves:

  • Precisely defining the Scope of Work — establishing what is and what is not included within the contract
  • Issuing and managing Post-Tender Clarifications (PTC) — addressing ambiguities and obtaining clarifications before the contract is formed

⚠️ Errors, ambiguities, or omissions at this stage are the seeds of future disputes. The Contractor's pricing decisions here will determine profitability — or losses — throughout the entire project.


2️⃣ Formation of Contract

📝 Transforming the tender into a binding legal relationship

This stage begins when:

Event Description
📨 Letter of Acceptance (LOA) The Employer issues the Letter of Acceptance to the Contractor — the contractual relationship is formally established
✍️ Contract Agreement Both Parties execute the formal Contract Agreement, confirming all agreed terms and conditions

📌 Under FIDIC, the Letter of Acceptance is the pivotal document — it is at this moment that the contract is formed, not at the signing of the Contract Agreement.


3️⃣ Commencement and Execution

🔨 The longest and most operationally intensive stage

This is the stage in which all Parties actively manage the contract to achieve the project's objectives. It encompasses:

Activity Responsible Party
🏗️ Physical construction and installation Contractor
📐 Design development and submission Contractor / Designer
🔍 Supervision, inspection, and testing Engineer
📋 Progress monitoring and reporting All Parties
💰 Interim Payment Certificates (IPC) Engineer
📩 Notices, instructions, and correspondence All Parties
⚠️ Claim submissions and responses Contractor / Engineer / Employer
🔄 Variation management Engineer / Employer

🎯 This is where contract management skills are tested most rigorously — and where the quality of the contractual relationship determines whether the project succeeds or descends into dispute.


4️⃣ Taking Over

🏁 Marking the transition of site responsibility

Taking Over occurs after:

Milestone Detail
✅ Tests on Completion All required pre-completion tests are carried out and passed successfully
📜 Taking Over Certificate (TOC) The Engineer issues the Taking Over Certificate to the Contractor
💰 Partial Release of Retention The Contractor is entitled to recover a portion of the Retention Money — typically 50%
🔄 Transfer of Site Responsibility Responsibility for the site transfers from the Contractor to the Employer

⚠️ The Taking Over Certificate is a critical contractual milestone — it triggers significant financial and legal consequences for both Parties.


5️⃣ Defects Notification Period (DNP)

🔧 Post-completion obligations and final handover

During the Defects Notification Period, the Contractor's obligations include:

Obligation Detail
🔨 Defect Rectification Identifying and remedying any defects that arise or are notified during the DNP
📐 As-Built Drawings Submission of final As-Built Drawings reflecting the completed works
📚 O&M Manuals Delivery of Operation and Maintenance Manuals to the Employer
🎓 Training Training of the Employer's operating and maintenance personnel

📌 Note: As-Built Drawings, O&M Manuals, and Training obligations may also be completed during the Execution Stage — many contracts require their progressive submission throughout construction rather than only at the end.


6️⃣ Final Completion

🎉 The formal conclusion of all contractual obligations

Final Completion marks the end of the contractual relationship and involves:

Event Detail
📜 Performance Certificate The Engineer issues the Performance Certificate — the Contractor's formal discharge from their obligations
💰 Final Release of Retention The remaining balance of Retention Money is released to the Contractor
🔒 Return of Performance Security The Employer returns the Performance Security (Performance Bond / Bank Guarantee) to the Contractor
📋 Final Payment Certificate The Engineer issues the Final Payment Certificate
💵 Final Statement The Contractor submits the Final Statement of account

♻️ Every Stage Carries More Than Just Procedural Steps

Each phase of the project lifecycle is not merely an administrative checkpoint. Every stage carries:

Element Description
⚖️ Contractual Rights and Obligations Specific entitlements and duties that arise — and can be lost — at each stage
📩 Notices and Correspondence Formal communications that must be managed with precision and within contractual timeframes
⚠️ Risks Exposures that must be anticipated, monitored, and mitigated
🛡️ Opportunities Windows to protect rights, establish entitlements, and minimise disputes

📌 The Strategic Value of Effective Contract Management

Effective contract management throughout the project lifecycle does not only help deliver the project on time and within budget.

It also makes a decisive contribution to minimising claims and disputes between the Parties — protecting the interests of all stakeholders and preserving the commercial viability of the project.


❓ Discussion Question

Which stage of the project lifecycle do you consider the most sensitive — and why?


🌐 For more content like this, visit our website and explore the free PM Guide Blog: https://pm-guide.net/blogs


Together, we build a better future in construction project management. Jean Zachary | Founder, PM Guide

shape-1

Behind every successful venture is an expert team

Technology evolves, and so do our solutions

Identify Your Needs

Let's discuss your business needs. Understanding your goals is crucial to get better results.

Tailored Solutions

Next, our team develop customized solutions and tools designed specifically for your business.

Ongoing Support

Our commitment doesn't end with implementation. We provide support to ensure continued success.

Our team is made up of passionate individuals

We are more than just a normal business!

Happy Clients

0 +

Happy Clients

0 +

الإمتحانات

Alex Miller
CEO
×

Hello! How may we assist you today?

Click to Chat